Action/Point Person

Expected Completion Date

Notes

Status

Fulfillment and ILL FG

FG discussed how the Vanguard decision worked out, and what way forward would be best for testing during the Test Phase of SILs (Vanguard) Decide how to integrate an ILL broker with Alma

Since GES proved successful in Vanguard, the group initially favored setting it up again in Test while also attempting to set up and test the alternative solution (the Illiad VDX Email Adapter) during the test phase.

This decision page was created.

Status
colourGreen
titleDone

Fulfillment and ILL FG

Group reviews and votes. Unanimous support for setting up GES and attempting to set up the alternative solution (the Illiad VDX Email Adapter) during the test phase. This ensures that if the alternative solution does not work, we still have the GES option to fall back on for Implementation.

Decision will be sent to Discovery FG, PPC, and ICs to inform.

Status
colourGreen
titleDone

Joe Ferrie

Dec 10, 2020

Revise based on new decision to move forward with supplier of last resort option. Add instructions for configuring supplier of last resort.