1

Check-in / updates

Information sharing and problem-solving

10

All

RMFG: working on finalizing testing documents and what to send to internal training. Also starting a discussion around OCLC updates. It would be nice to know when we can implement them and what the scope would be since some campuses are trying to re-evaluate workflows that might change if they are set up.

TSELG: the group made decisions about UC ETDs. RMFG was asked to investigate 4 issues: standardization of MARC records; distribution of MARC records from Merritt to NZ; distribution of revised Alma NZ records back to Merritt; distribution of MARC records to OCLC.

DISCOVERY: working on pulling together recommendations made in our subgroup Primo VE usability testing work in December. We plan to have our summarized recommendations for test load testing ready and delivered to IC’s by March 1st. Topics are based upon ExL configuration workbook forms. Starting to discuss renaming UC-eLinks and where Help link(s) should go in the Primo VE interface and to whom those links should connect users to (local campus vs. CDL).

DCFG: No update this week. Waiting for next week’s delivery of Primo VE.

Fulfillment and ILL: Updated vote on (Test Load through Post Go-Live) Alma/VDX NCIP Integration , and finishing getting our testing materials ready for Test Phase. We have a new FG member representing UCSC starting next week- Mallory DeBartollo.

2

Decisions

Approve decisions

Discussion topic: how to approach a decision that is appropriate for a FG but where none of the current FG members have the needed expertise (HathiTrust is one of the example)

15

Josephine, Liz

Primo VE Default Search Profile Configuration 

  • There is a pros and cons list that shows how they thought it through

  • Place holder text when you first see the box “Books, articles. and more”

  • Will try boosting and test out optimum percentage to boost; the smaller the campus, the higher the percentage needed to boost to make the home campus be the top option.

  • Will test “easy activation” impact on UX - essentially, what will get patrons to a satisfying level of results

  • Best way to read table plus and minus symbols is whether the group decided that the impact would be an improvement or a detraction.

SILS Metadata Exports to Support UC Print Digitization, Access, and Preservation

  • Discovery’s Primo VE Default Search Profile Con

  •  
3

Open Access

Discuss the questions from PSELG

15

Beth

Questions from PSELG to PPC

4

Test Load

When can we share the document Collaborative Workflow Testing and with whom (cohort and beyond)?

Scheduling the work, especially those needing cross-FG coordination

25

All

Vanguard Testing Worksheet for PPC

Collaborative Workflow Testing

(From Liz) 2 specific questions:

1.) How to document/track work? Shared google docs or individual FG docs linked to the testing sheet?

2.) How to order these so that dependent/related workflows are tested in the right order? For example: re-linking portfolios to/from CZ bibs should come before e-resource receipt/processing so that the building blocks are in place

5

MVP

Share the experience using the MVP document

Have any item on Systemwide Work sheet been moved to the MVP document?

MVP lightening round is happening next week at SILS Chairs on Wednesday 2/10. Any questions?

10

Xiaoli

MVP document

6

What needs to be in OCLC?

Do we need to catalog everything in OCLC?

Is OCLC record number still very important that we need to have it in IZ/NZ?

10

All

DISCUSS AT NEXT MEETING

  • Next steps:

    • do an environmental scan - what are other Alma campuses doing? What is the impact of moving away from OCLC?

      • Groups that would start:

        • RMFG

        • ACQ-ERM

        • Discovery

        • Special Collections

      • bring findings back to PPC

 

 

7

PM Update

Awareness of what’s happening / coming soon in the project

5

Christine

  • Test load:

Merced’s Alma environment is expected to be delivered next week. Primo VE is still expected for all campuses on 2/26.

  • Meetings:

Congratulations to Liz M and Lisa for their successful Import Profiles meeting!

List of meetings on Basecamp

  • Thu Feb 25: Letters, Notices & Jobs - Questions due 2/22

  • Mon, Mar 8: GOBI orders / API ordering (requested in VG workshop)

  • Thu, Mar 11: Integrations Overview (including Online Payment Options - requested in VG workshop)

    • Will cover how to use To Do list and then go over basics of the listed integrations.

  • Thu Mar 25: Fiscal Close - UC-led meeting

  • Thu, Apr 1: E-Resources Data Cleanup in Alma w/focus on P2E

  • Mon, Apr 12: AFN Configuration Review 

8

Homework

9

Parking Lot

  • For January: CDL shared services In progress

    • Who from CDL should PPC liaise with?

    • Can CDL create a list of shared services that they will be providing? Would like to create a document that could be shared with cohort.

    • What services is CDL currently doing? What services will CDL be providing in production?

10

TOTAL