Determine whether to harmonize local fields for display, search, and facet in Primo VE.

Decision

Local campuses should reserve local_field_51 through local_field_100 for harmonized display, search, and faceting in the future. This decision should be revisited within 6 months of go live.

Owning group

Discovery FG

Approver

PPC

Stakeholders

R = Discovery FG, RMFG
A = PPC
C = RMFG
I = ICs

Decision-making process

Priority

Mandatory before Go-live

Due date

...

Local campuses should use local_field_1 through local_field_50 for display, search and faceting. Local_field_51 through local_field_100 should be reserved for centrally managed display, search and faceting.

This decision should be revisited within 6 months of go live to identify potential targets for harmonization.

Reasoning

Central management of local fields 51-100 in the NZ allows distribution of the fields to the IZ; at the point of distribution, any local customizations that use local fields 51-100 may be overwritten. (See ExLibris Central Management in Collaborative Networks documentation).

...

Action/Point Person

Expected Completion Date

Notes

Status

Assess already-Alma campus use of local fields for search & facet and identify needs of two new-to-Alma campuses (UCB & UCLA) / Lisa N. and Sharon S.

May 1, 2021

MARC facet, search, display spreadsheet

Complete

Consult with RMFG

June 4, 2021

Approved by PPC