Item

Desired Outcome

Time

Who

Notes

Decisions

Actions

1

Check-in / Logistics

Report any major changes in availability / circumstances

15

Chairs

Reminder: There’s a slack channel for the ELUNA Regional User’s Group of California that could be useful for posing questions. Jeremy and a few others are already using it.

Formal round robin: how’s it going with your current implementation activities?

2

ILS Data cleanup / Patron Data groups / PPC

ICs know how it’s going with these groups

PPC: All-decision Rollup

5

Chairs

3

Training - Alma Certification

Understand who is going to get Alma Certified

0

Carlo

  • Who’s going to get certified / already certified? (This list from Slack poll 7/14/20)

    • Already certified: @Sarah Lindsey (UCSC), @Gillian Keleher, UCSC (she/her), @Robin Gustafson (UCD), @Ramon Barcia (UCR), @Jeremy Hobbs (UCSB)

    • Plan to be certified: @Lynne Grigsby, @Susan Boone (UCSF), @Alison Ray (CDL), @Tom Bustos (UCM), @Greg Ferguson (UCSD), @Carlo Medina

4

Timeline review

Stay up to date on timeline / deadlines: Basecamp To-Dos

10

Caitlin

Basic review with focus on testing / reporting.

Who’s doing test plans? Where are those materials?

  • Local SILS groups

  • ILSDC

  • RM, Acq/ERM, Fulfillment FGs

  • Other?

5

Assessment & Test Planning (Due 7/16)

Report on work (Gillian, Sarah, Jeremy, Ramon, Robin)

10

Alma campuses

6

Vanguard testing

Start to set expectations for vanguard testing by non-vanguard campuses

25

Caitlin

ExL on 7/9:

  • One sysadmin account per VG who can then make other accounts as needed

  • Not everyone needs NZ access, because NZ data is populated out to the IZ Almas and Primo - so better to see it there, not in the actual NZ.

Moving forward:

  • Note that there’s a patron data / acq data privacy group started in WG for examining how do we address privacy issues in testing and in consortial work.

  • What is the best “Default” thing to do → make a shared view-only account for Sept, then set up meetings / Q&As for Oct?

    • Guidelines:

      • make as few accounts as necessary

      • Give VG campuses some space to assess in Sept

  • Set up some template for asking who wants access and why

  • Plan the culmination of Vanguard and how to show the results of what we learned

    • Decouple “having access” from “learning lessons”

    • PMs check in with ExL about what they have planned for lessons learned time at the end of the Vanguard phase

    • Who does the “lessons learned”? → The VG ICs and the relevant PPC/FG folks. Scope minimum expectations for lessons learned.

7

Other / Homework

5

8

TOTAL

80 60 / 90