Scope

Test Load through Post Go-Live

Description

Should UCs implement NCIP integration of Alma and VDX

Decision

  1. We recommend that all institutions implement an NCIP2 integration between VDX and Alma of the Accept Item message, and the borrower Check In Item message. This FG will provide a harmonized set of instructions for configuring the NCIP integration.

  2. Because all institutions agree to this harmonization, we recommend that if possible the initial installation costs for the NCIP integration be funded out of the SILS budget.

Owning group

Fulfillment & ILL (SILS-FG-FULFILL-L@LISTSERV.UCOP.EDU)

Approver

PPC

Stakeholders

R = Fulfillment and ILL FG
A = Fulfillment and ILL FG
C = PPC
I = ICs

Decision-making process

Fist of 5

Priority

High

Due date

D

Decided

Recommendation

The FG recommends that all UC institutions integrate VDX with Alma using the NCIP 2 Accept Item and Check In Item messages. (Pre-SILS Alma institutions have already implemented at least the Accept Item message.)

...

Institutions that currently have NCIP integration (UCD, UCSC, UCSB, UCI, UCR) can retain their current NCIP integrationsconfigurations, but may wish to harmonize their implementations post go-live, as they are not uniform.

Background

NCIP 2 is a standard protocol that enables integration between external systems, including interlibrary loan brokers, and ILS circulation systems. VDX (via the OCLC NCIP gateway) and Alma both support this protocol, and integrations have already been implemented at the UC institutions that installed Alma prior to the SILS.

...

Action/Point Person

Expected Completion Date

Notes

Status

Fulfillment and ILL FG

Group meets and discuss standardizing NCIP integration across UCs, to avoid manual creation and deletion of on-the-fly records during the fulfillment and ILL processes.

Before SILS, each institution worked independently with OCLC and Ex Libris to achieve the integration.

The group feels that the best way forward is to propose that a representative of the SILS cohort negotiate an agreement with OCLC to provide the NCIP integration to institutions that are not yet integrated with Alma.

Status
colourGreen
titleDone

Fulfillment and ILL FG

FG meets and votes on decision page. It passes with unanimous support.

Status
colourGreen
titleDone

PPC

PPC voted to move foward with unanimous support.

PPC Chair will reach out to CDL rep about starting a negotiation for purchase of NCIP.

Status
colourGreen
titleDone

Fulfillment and ILL FG

Jan 22, 2020

Based on new analysis and consultation, reset status to IN PROGRESS and draft new recommendations

Status
colourGreen
titleDone

Chairs

Feb 5, 2021

Received feedback from WG regarding this decision, with a strong recommendation to harmonize across institutions.

Status
colourGreen
titleDone

Fulfillment and ILL FG

Feb 11, 2021

Consider new revision and validate with local teams that a harmonized approach is desired. Revised decision is motivated by recommendations from WG after this FG presented its report on 02/05/2021.

Status
colourYellowGreen
titleIN PROGRESSDone