  • Phase 4 early kickoffs for Implementation Coordinators and Project Management Operation Leads - February 2020

  • Phase 4 kickoffs for all groups - April 2020

  • Premortem risk assessment for all groups - April/May 2020

  • Project wiki opens - June 2020

  • Work plans submitted to SILS WG for Shared Governance Task Force (SGTF), and Operation Leads groups (Project Manager Leads and Communication Leads) - June 2020

  • SILS Service Manager starts - July 1, 2020

  • Budget/Finance projection for campuses (CoUL) - July/Aug 2020

  • Mid-term report to CoUL - April 2021

  • CoUL & DOC review & approve the proposed SILS ongoing shared governance (will include shared governance proposal model(s) and proposed timeline to transition to operational shared governance, and recommendation for when phase 4 will end) - late June 2021

  • SILS go-live on July 27, 2021

  • Transition to Ex Libris support: August - October 2021

  • SILS post-go-live work TBD : September - December 2021

  • End of Phase 4: December 2223, 2021 (subject to final approval by CoUL in June)

  • Final report to CoUL in alignment with phase 4 completion

...