Legend: NOT STARTED IN PROGRESS STALLED DECIDED

Status

IN PROGRESS

Scope

IMPLEMENTATION

Description

Determine whether to open Basecamp to more users during the full implementation phase. If so, determine the conditions for opening Basecamp more broadly.

Decision

Owning group

Op Leads sils-op-leads-l@listserv.ucop.edu

Approver

ICs, PPC

Stakeholders

R = Op Leads
A = ICs, PPC
C = SILS Chairs, Ex Libris, ICs, PPC, Internal Training co-chairs
I = cohort, Ex Libris

Decision-making process

DISCUSS with chairs to understand whether this would be beneficial and desirable. If yes, continue.

CONSULT with stakeholders to understand the tradeoffs and what conditions and best practices should be put in place.

DECIDE who is eligible for a Basecamp account, how they get the account, and what conditions must they meet (e.g., read and agree to best practices.)

Priority

Due date

Recommendation

During the full implementation phase starting in November, grant Basecamp accounts upon request on an as-needed basis. Approval is granted by the requestor’s group chairs or IC. Chairs/IC will request the account from Ex Libris via Basecamp and will inform the account requester of the best practices document.

Reasoning

All campuses will participate in the Implementation phase and good communication about the project will be critical. Chairs and ICs reported some frustration from cohort members and local implementation teams who did not have full access to Basecamp and therefore had to go through others to get the information they needed.

Best Practices

  • Before posting your question to Basecamp:

    • First, pose your question to your SILS group. Your group may know the answer.

    • Second, search posts in Basecamp to see if your question has already been answered.

    • Third, search Ex Libris documentation; Google search works well (Ex Libris documentation is indexed by Google.)

    • If your question is not answered in the first three steps, then proceed to post it to the Basecamp message board.

  • Set up your notifications. You may want to consider a daily digest rather than being notified for each new message. Click on your Basecamp avatar in the upper right corner to access notification options.

  • Do not check off “To Do” tasks as “done”. Only Ex Libris project managers should do this.

  • Archive your messages on the message board when they are answered. You will still be able to find archived messages using search.

  • Consider the urgency of your question. Are you asking about something coming in two months or do you have an immediate and urgent need for this information? Ex Libris strives to respond to or acknowledge your post within 1-2 business days.

  • Do not use Pings. Read more about why they are not allowed.

  • Read the "message board rules of the road"
 for more information on using message boards.

  • Administrators reserve the right to remove accounts.

Background

As we enter the full implementation phase, revisit our policy on limiting Basecamp accounts. Consider opening Basecamp on an as-needed basis to local implementation team members and cohort members. Currently, about 65 people have Basecamp accounts.

Basecamp access was limited during the vanguard phase to:

  • Implementation Coordinators (ICs)

  • Internal Training members (IT)

  • Chairs

  • Op Leads: Project managers, Communication leads, SILS Service Manager

Why was access limited?

  • To avoid duplication of many people posting questions on the same issue.

  • Fewer people with accounts meant it was easier to prioritize time-critical questions.

Why are we revisiting this policy now?

  • It’s been challenging for people without accounts to get the detailed information they need on Basecamp. Public links do not let you see the details of tickets.

Dependencies

  • Ensure our practices are in alignment with Ex Libris' policies and expectations.

Questions to consider

  1. Will adding more people to Basecamp dilute its utility for the core user groups, ICs, PPC, and IT?

  2. Will adding more people to Basecamp create too much work in answering questions and troubleshooting problems about Basecamp?

  3. What’s the best way to share best practices and what happens if users do not follow them?

  4. Limit to only cohort? Include local implementation team members who are not in the cohort? Allow ICs and others chairs to determine who on the local teams should be included?

  5. When should access begin? Should it begin immediately to allow new users to get used to Basecamp before Implementation begins or wait until Implementation phase launches on Nov 5?

Action Log

Action/Point Person

Expected Completion Date

Notes

Status

Determine with stakeholders whether opening Basecamp more broadly would be beneficial and desirable. (PMs)

SILS Chairs meeting 9/9/20. Poll results: 3 “yes”, 3 “no”, 13 “maybe”. Proceed to consult.

Done

Consult with stakeholders to understand the tradeoffs and what conditions and best practices should be put in place. (PMs)

Op Leads meeting 9/10/20

PM meeting with Marci 9/10/20 Done!

PPC meeting 9/11/20

IC meeting 9/17/20

IT meeting (ask via slack)

Create a decision page. (PMs)

Done

Draft Basecamp best practices document. (Op Leads)

Op Leads to start a draft.

Done

Get feedback on the best practices document from chairs and ICs. (PMs)

SILS Chairs, ICs, PPC, IT

In progress

Post the final version of Basecamp best practices to Basecamp Docs & Files and add a link to this decision page. (PMs)

Determine when to put this decision into practice, and when & how to communicate out.

  • Start immediately after best practices and consultations are done.

  • Use informal word of mouth or send a broader communication such as SILS cohort email/slack?

Communicate to chairs

Communicate to interested parties that accounts will be granted upon request on an as-needed basis. (PMs)

TBD