Decide how the UCs will approach implelmenting WorldCat Daily Updates

Decision

see below

Owning group

RMFG

Approver

PPC

Stakeholders

R = RMFG
A = RMFG
C = CDL
I = All-cohort

Decision-making process

Priority

Due date

Recommendation

WorldShare Collections (created by UCSD):

    Non-serials

    Serials:

Alma production import profiles:

Reasoning

Assessment

Background

WorldCat updates is a process where OCLC will deliver a set of records to a library based on actions taken in OCLC (including editing, merging, setting and unsetting holdings) and based on a “query collection” set up in WorldShare. In the UC case, that includes a list of holdings symbols and what types of changes we want to trigger record delivery. If a change listed in our collection happens to a record with one of the holdings symbols in the list, OCLC delivers a new copy of that record for central processing as we see fit. Records get delivered in sets that include:

    WorldCat updates does not set or unset holdings at any point in the process. The only connection between WorldCat Updates and OCLC holdings is that the WorldCat Updates relies on a set of holdings symbols to decide which records to deliver. OCLC does not add records to Alma for us and it doesn’t delete them, it just sends us files of records for us to then add as we see fit. In a consortium it makes the most sense to do this in the NZ since it reduces duplication. For example, if 7 of us have holdings set on a given journal record and the title ceases publication. If all 7 campuses have their own version of WorldCat updates set up then they all get the same notification that the title ceased. Then all 7 of them, likely at different times, go to update the NZ copy of the record with the new closed dates. The first campus to do that would be the one to actually make the correction and the other 6 would just be checking and possibly overlaying a record for no reason. If we were to instead load that record one time, centrally, it saves everyone the trouble. 

Action Log

Action/Point Person

Expected Completion Date

Notes

Status

RMFG draft

05/2021

done

Campus review

06/07/2021

done

RMFG approval

06/08/2021

done

PPC approval

06/11/2021