Coordinated Ten Campus + SCP Implementation of Official RDA

Coordinated Ten Campus + SCP Implementation of Official RDA

See Best Practices for Decision Pages and Tags for groups
Legend: not started IN PROGRESS STALLED decided

Status

DECIDED

Description

The original RDA Toolkit (https://original.rdatoolkit.org/) is based on the FRBR, FRAD, and FRSAD conceptual models and is the version we have been using in our cataloging for the past decade or so. After IFLA consolidated FRBR, FRAD, and FRSAD into the IFLA Library Reference Model (LRM), the RDA Toolkit underwent a Restructure and Redesign Project (3R Project) to, in part, align RDA with LRM and improve the Toolkit functionality. The new version of the RDA Toolkit is known as the official RDA Toolkit (https://access.rdatoolkit.org/).

The PCC Policy Committee announced that PCC will have a rolling implementation from May 1, 2024 to April 30, 2027. This 3-year rolling implementation will allow institutions to transition to the official RDA Toolkit before the removal of the original RDA Toolkit in May 2027.

The Resource Management OST and the Cataloging and Metadata Common Knowledge Group have had discussions on whether a coordinated implementation would be preferable to campuses implementing on their own individual timelines.

Decision summary

Resource Management recommends that UC harmonize the implementation to official RDA by all campuses and SCP as a single project. Because all campuses and SCP will need to implement, a coordinated effort will reduce redundancy in training and documentation efforts.

Owning group

Resource Management

Approver

Resource Management

Consulted

CMCKG

Informed

 

Decision-making process

Discussion and Consensus

Priority

High

Target decision date

February 26, 2026

Date decided

February 26, 2026

Recommendation

Resource Management recommends that UC harmonize the implementation to official RDA by all campuses and SCP as a single project. Because all campuses and SCP will need to implement, a coordinated effort will reduce redundancy in training and documentation efforts. In order to meet this need, it is recommended that a project team be formed with members from RM, CMCKG and other interested parties who have experience writing policy statements. The deliverables of the team could be:

  • A timeline for UC-wide implementation

  • Development of a UC-wide, RDA-compliant cataloging manual for existing and new catalogers

  • Training plan for UC-wide implementation, ideally utilizing PCC training modules

Impact

Stakeholder group

Impact

Stakeholder group

Impact

OT/LG

Approval of project team in consultation with DOC

Resource Management

Final approval of timeline, training plan, manual; host documentation

CMCKG

Partner in communication and project team participation

Related Documentation

Follow-Up Action Log

Action/Point Person

Expected Completion Date

Notes

Status

Action/Point Person

Expected Completion Date

Notes

Status

C. Busselen/A. Baron

Mar 10, 2026

Communicate decision to harmonize to CMCKG and beyond

DONE

C. Busselen

Mar 31, 2026

Draft charge for project team for approval by OT/LG (with consultation by DOC)

DONE