Item | Desired Outcome | Time | Who | Notes | Decisions | Actions | |
---|---|---|---|---|---|---|---|
1 | Check-in / updates | Information sharing and problem-solving | 5 | All | RMFG: working through MVP items; had an informal session with Luiz Mendes at CSUN about authority control in Alma; Liz and Sarah have a standing meeting with the CDL ICs until the end of September DCFG: No new updates, other than that we’re investigating how to get rights information and campus affiliation into records we’re harvesting from Calisphere. | ||
2 | Decisions | Discuss and approve proposed decisions | 25 | (Go-live and beyond) MARC field to suppress bibliographic records from discovery network | |||
3 | Shareable MVP | https://docs.google.com/spreadsheets/d/1gpYQWYpt4GYMLWoVQHrKRlKwY6pMu_2eX78L1C-hPNI/edit#gid=0 | 0 | Christine | A gentle reminder: Please complete the missing parts on the new MVP doc/determine new deadline for completion. Refer to the PPC slack message on 5/27 for more details. | ||
4 | MVP - Primo VE Configuration needing Collaborative Work, including Display Logic Rules | From the Primo VE workshops: what areas need additional review/collaboration for configuration? Examples: Display Logic Rules, General Electronic Services, etc. that may need discussion across functional areas including e-resources management, fulfillment, CDL for NZ-level configuration. How should these collaborative areas in Discovery be addressed? What is currently on MVP to represent this, and if needing more, how should these items be represented (& with what ownership)? | 15 | Lisa | Lisa: it’s a big issue that impacts a lot of areas and might be good to do some messaging and start thinking about next steps. Do we need a subgroup? Are there minimums that need to be in place for Day 1? Jess: recent Primo trainings have surfaced some areas that weren’t on the radar before, some might be better candidates for post go-live. Agree that a subgroup is probably a good idea Next steps: AEFG already Alma campuses document their settings and identify critical ones, then reach out to Disco and CDL | ||
5 | EUOS (recurring) | https://docs.google.com/document/d/19pE99m3xZKp52BJVCBElm_d4bMPCpzRQt1-cW6gf_hQ/edit Soft deadline for when decisions that affect everyone can be completed | 10 | Claudia | Continued from last meeting: RMFG: June 8 DFG: June 8 AEFG: Working on developing Troubleshooting Decision Page to review at June 11th PPC (AEFG MVP 008), involves CDL coordination, will incorporate follow-up with EUOS and ICs. Ongoing: make sure we keep the public service components in mind as we keep making decisions. PSELG is also going to keep monitoring discussions | To be shared with ICs and EUOS | |
6 | PM Update | Awareness of what’s happening / coming soon in the project | 0 | Christine | Meetings For Monday project updates and office hours, feel free to skip and watch the recording later if there are no topics or if topics are not a subject of interest.
Details Regarding Opening SalesForce Cases
| ||
7 | Homework | ||||||
8 | Parking Lot | Future meeting:
| |||||
9 | TOTAL | 90/90 |
...