Coordinate with Discovery FG on Get It at UC image file. Lisa S.

Early June

5/25 Lisa S. messaged Jess/Josephine at Discovery FG to confirm this interdependency. Lisa S. gathering sizes needed based on UCD and from CDL - will follow up w/ Kimmy at UCD who created initial graphic.

Done

Coordinate with CDL for planning of project - how to best scale updates to work with multiple campus updates simultaneously.

7/1/2021

Conversations started earlier in May. Increasingly entering into AEFG discussion agenda.

6/14 Meeting with AEFG and Alison. Subsequent meetings with Lisa M./ Nga for CDL and Lisa S. / Carla for AEFG.

Preliminary planning DONE

Project planning: In progress - see Meeting Notes: 6/18, 6/25, 7/1.

Coordinate with ICs via Susan as they are reviewing this item, discussing Base URLs, etc.

5/26-27/2021 with follow-up as needed after IC

Reviewed Basecamp item that Le provided re: updating content providers. Formulated language for IC 5/27 agenda re: AEFG MVP 006 and actions to date, implications for coordination and dependencies (e.g., image file needs as above).

Done

Gather image filetypes and sizes, confirm w/ CDL, identify locations of files for URL purposes (in case where content provider wants URL for image vs. image file). Share with Kimmy for image creation. / Lisa S.

Image creation done. Confirming with CDL that image location can be on CDL servers (vs. Resource Lake on Google Drive)

In progress for file location.

Finalize and approve decision page - AEFG stage.

7/1/2021

To what extent can decision page go forward before the guidance documentation is finalized? Assuming it is somewhat tightly coupled for coordinating technical, discovery implications, patron expectations.

Decision page scope is structure of the project, guiding documentation to follow for Launch Session.

Approved via Slack/email (no AEFG meeting 6/30).

Done

PPC approval of decision page.

7/2/2021

Done

Distribution.Pending

7/7/2021

To IC via Slack. Email to Stacy with EUOS.

Done

Confirm e-resources subgroup, schedule and announce Launch Session.

7/9/2021

Launch Session on July 21, 9-10:30am. Email listserv, Slack channel, and Google Drive access finalized 7/16.

PendingDone

Develop documentation for guiding CDL/Campus Coordination project. Include clear indications of content providers that campuses can update without needing CDL coordination.

mid-July

Need to formulate how to identify these resources. To what extent are these not represented by SFX reports?

CDL is reviewing list from SFX Query 2, assessing what will be handled locally vs. centrally

In progress to finalize for Launch Session.

Project Coordination

Go-Live to Late October (90 days from go-live)

Pending

Assessment/ follow-up/ stabilization.

November-December

Pending