Stage & Timeline

Major Tasks

Notes

  1. Planning & Kickoff

March - May 2020

The PM Leads will develop a plan that includes a timeline for completing their work and deliverables. 

Deliver work plan to the SILS Working Group for review and endorsement at June 12, 2020 meeting.


Set up project collaboration tools

Google shared drive, Confluence, listserv, slack

Design documentation templates and best practices, including for minutes and tracking action and decision items, to be shared with all cohort groups for their use

Meeting notes template, Decision template, Task report, Team charter.

Kickoff all groups

Host kickoff guidance meeting for chairs; provide sample kickoff agenda

Taking the temperature survey

Provide chairs with a survey to assess the baseline understanding of the project by members

Pre-mortem and risk mitigation

Premortem summary and actions for Cohort

Premortem summary and actions for WG




2. Project support 

June 2020 - July 2021

Manage and refine the overall project timeline, in coordination with the SILS Working Group and coordinator groups.

Week-by-week Phase 4 Master Timeline 

Timeline overview on Confluence (milestones)

Manage and refine the implementation timeline and meeting and training schedules working with the Ex Libris project manager and in consultation with coordinator groups.

Twice weekly meetings

Implementation timeline

Ex Libris meetings

Training calendars

Manage and refine the overall project Responsibility Assignment Matrix (i.e. RACI), in coordination with the SILS Working Group and coordinator groups.

RACI will be done for each decision.

Master RACI for major decisions

Project co-managers manage the SILS Working Group decision slate

/wiki/spaces/SWP4/pages/454066363 

As embedded staff, the project managers will attend coordinator group meetings and support the work of the chair(s) and members. Additional work will include management of the coordinator group’s minutes, timeline and deadlines, discussion facilitation as needed, and understanding and communicating dependencies.

ICs = Lena Zentall

PPC = Christine Barone

Training = Neil Weingarten (through mid-November 2020); Joanna Kang (starting mid-November 2020-April 2021)

Each embedded project manager will provide guidance to the groups and subgroups that correspond with their applicable coordinator group. Through what can be considered a consultancy service, guidance to functional groups and subgroups might include project management and facilitation advice. 

Periodic training webinars on project tools and best practices

Facilitate all-chairs meeting to ensure robust cross-group collaboration

Currently planned for 60 minutes every two weeks (chairs + SILS co-chairs, PM Leads, Com Leads, SSM)

Report on project status

SILS Project Reporting 

Mid-term report to CoUL (WG) March April 2021: will include a proposal for UCLAS-integrated SILS shared governance and a recommendation for when phase 4 will end (sometime in fall/winter 2021).

Onboard new SILS cohort members that join mid-phase; manage offboarding.


Manage user permissions for project tools. 





3. Post-Go-Live

August 2021 - December 2021


Post mortem


Contribute to final report

Final report to CoUL (WG) (Sep/Dec 2021) decided to deliver after the end of phase 4 in Feb 2022

Offboard SILS cohort members 

Remove access to project collaboration tools

Manage project documentation 


Decommission project collaboration tools or handoff to ongoing governance group





...