Item | Desired Outcome | Time | Who | Notes | Decisions | Actions | |
---|---|---|---|---|---|---|---|
1 | Check-in / Logistics / Any issues with testing? | Report any major changes in availability / circumstances Anything to report on the test load? | 10 | Carlo |
| ||
2 | ILS Data cleanup / Patron Data groups / PPC |
| 10 | Carlo, Tom |
|
| |
3 | Timeline review / PM update
| Stay up to date on timeline / deadlines | 5 | Lena |
| ||
4 | Update and questions from Alma Accounts Task Force |
| Lynne, Gillian |
| |||
5 | Questions from slack |
| 10 | ||||
6 | Other / Homework | 0 | Tom |
| |||
7 | Q&A (recurring) | Q&A during the IC meeting as a first stop before asking a question on Basecamp. If it’s time-sensitive, post to slack (IC channel, SILS Chairs are good options) Any issues that we want to seek broader input from other consortia? | TBD | Carlo | |||
8 | Questions for Ex Libris PM (recurring) Post questions in Basecamp as they come up. It’s open 24/7! | Note: We lose in efficiency and we may lose in translation when questions go through the PMs. When topics come up that should logically go to Basecamp to the Ex Libris consultants, invite an IC (or appropriate person) to take point on that issue. | 0 | Lena | Answers from Marci 3/25: Slow response on Basecamp Q: When will ExL be answering questions posted to Basecamp on the integrations list? Alison posted a question quite a while ago. A: Marci reviews outstanding tasks on Fridays with the team. ExL is attentive to the integrations list for questions. If you are not getting any response, post to the original question as a poke to get ExL’s attention. Primo VE instance for Workshop
UCD Escalation (3/17) Status as of 3/25: “The Migration team was working on copying their live environment to the AMO's implementation environment over this past week - so they can work on it and test proposed fixes to it. We expect additional updates on their progress and next steps next week.” | ||
9 | Parking lot | 0 |
| ||||
10 | TOTAL | 50/90 | Review decisions and actions. |