Implementation Timeline
Major Work and Milestones
Status: In progress DONE late
Blue = SILS Admin activity
Yellow = Implementation activity
Green = Ex Libris activity
Italics = unconfirmed/estimated and subject to change
Phase | Task | Owner | Deadline | Status | Notes |
---|---|---|---|---|---|
Onboarding March - May 2020 | SILS Project Phase 4 Kickoff - Wave 1 | SILS PMs / WG volunteers | Feb 26, 2020 | DONE | |
Implementation Coordinators start meeting weekly | ICs | Mar 13, 2020 | Done | ||
SILS Phase 4 Kickoff & Orientation - Wave 2 | SILS PMs / WG volunteers | Apr 3, 2020 | done | ||
Basecamp provisioned | Ex Libris | Apr 6, 2020 | Done | ||
SILS generic sandboxes provisioned | Ex Libris | Apr 6, 2020 | Done | ||
SILS Groups kickoffs, lead by Chairs | SILS Chairs / PMs | Apr 17, 2020 | DONE | Each group's chair will lead a kickoff as part of their first meeting. | |
Approve the vanguard slate | ICs | Apr 17, 2020 | Done | Needs approval at WG meeting 4/17 (approved!) | |
Implementation Form finished | ICs | Apr 17, 2020 | DONE | ||
Finish Getting to know Alma Training | ICs | Apr 24, 2020 | DONE | ||
Intro to the Zones overview | Ex Libris | May 11, 2020 | DONE | ||
Network Zone Q&As | ICs / PPC / FGs / ELs / Ex Libris | May 18-Jun 5 | DONE | ||
Finish 3rd party integrations form | ICs | May 29, 2020 | DONE | ||
Vanguard June - Oct 2020 | Vanguard kickoff call | Ex Libris | Jun 15, 2020 | DONE | Vanguard institutions: Berkeley, CDL, UCLA, San Diego, San Francisco, Santa Barbara |
Vanguard Alma training (essentials, admin fundamentals, etc.) | Ex Libris / SILS Internal Training Group | July - August 2020 | DONE | See schedule on Vanguard Alma & Primo VE Trainings | |
Vanguard data DRAFT deadline | ICs | Jul 17, 2020 | DONE |
| |
Vanguard data FINAL deadline | ICs | Jul 31, 2020 | DONE |
| |
Vanguard test load start | Ex Libris | Aug 9, 2020 | DONE |
| |
Vanguard configuration DRAFT deadline | ICs | Aug 14, 2020 | DONE |
| |
Vanguard configuration FINAL deadline | ICs | Aug 21, 2020 | done |
| |
Vanguard Fulfillment Network configuration DRAFT deadline | CDL IC + Fulfillment FG | Aug 21, 2020 | done |
| |
Fall semester instruction begins |
| Aug 26, 2020 |
| UCB and UCM; UCD Law 8/24 | |
Vanguard Fulfillment Network configuration FINAL deadline | CDL IC + Fulfillment FG | Aug 28, 2020 | DONE |
| |
Vanguard "Alma Essentials" and "Administration Fundamental" Training completed | ICs + testers + local vanguard implementation teams | Aug 31, 2020 | DONE | Except Analytics demo on 10/12 | |
Vanguard Primo VE training | Ex Libris / SILS Internal Training Group | September 2020 | DONE | ||
Vanguard test load delivery - Alma | Ex Libris | Sep 4, 2020 | DONE | Delivered on schedule: Sep 4 (UCSD, UCSF, SCP IZ) Delayed: Sep 5 (UCLA), Sep 7 (UCSB), Sep 9 (NZ), Sep 18 (UCB) | |
Vanguard Alma special meeting: Using Alma for Data Review | Ex Libris | Sep 10, 2020 | DONE |
| |
Vanguard delivery - Primo VE | Ex Libris | Sep 16, 2020 | DONE | Delivered on schedule: UCSD, UCSF, UCLA, UCSB Delayed until Sep 18: Network Zone and UCB | |
Vanguard Primo VE special meeting: First look | Ex Libris | Sep 17, 2020 |
| ||
Fall quarter instruction begins |
| Oct 1, 2020 |
| UCI, UCLA, UCR, UCSB, UCSC, UCSD, UCSF except UCD 9/30 | |
Vanguard Alma workshops | Ex Libris / SILS Internal Training Group | October 2-9, 2020 |
| See Internal Training’s Vanguard October Workshop Schedule | |
Vanguard Alma & Primo VE certification begins | SILS Internal Training Group | Sep 2020 - July 2021 | DONE | Contact Internal Training for more information 1 staff member must be Alma/Primo VE certified by Test Load to edit configurations. 2 staff members must be Alma/Primo VE certified before go-live. | |
Vanguard completion (lessons learned) | Ex Libris / UC | Nov 2, 2020 | DONE |
| |
Implementation Nov '20 - July '21 | Implementation Kickoff | Ex Libris | Nov 5, 2020 | DONE |
|
Migration meetings | Ex Libris / UC | November 6-20, 2020 | Done | See schedule on Ex Libris Meetings | |
Alma training (essentials, admin fundamentals, etc.) | Ex Libris / SILS Internal Training Group | Nov 4, 2020 - February 8, 2021 | Done | See schedule for Implementation Alma & Primo VE Trainings | |
Provide population order for the Network Zone | Resource Management FG | Dec 4, 2020 | DONE |
| |
Download latest auto-extract kit [Voyager only] | ICs | Dec 4, 2020 | DONE |
| |
Download and install the latest Migration File Validation tool [III and Alma] | ICs | Dec 4, 2020 | DONE |
| |
Confirm campus contacts for Test Load tracking in Sales Force | ICs | Dec 4, 2020 | DONE |
| |
Draft Migration forms due [III, Voyager, and WMS] | ICs | Dec 7, 2020 | DONE |
| |
Retain local extensions | ICs | Dec 11, 2020 | DONE |
| |
Submit data files to EXL MFT server [III, Voyager, WMS and Alma] | ICs | Dec 14, 2020 | DONE |
| |
Final Migration form [III, Voyager and WMS] | ICs | Dec 14, 2020 | DONE |
| |
Field Mapping form [III and WMS] | ICs | Dec 14, 2020 | DONE |
| |
P2E file [N/A for Alma] | ICs (except existing Alma campuses) | Dec 14, 2020 | DONE |
| |
Delivered Files list [III, WMS and Alma] | ICs | Dec 14, 2020 | DONE |
| |
360/Intota reports and "360 and Intota to Alma Migration" form (if applicable) | ICs | Dec 14, 2020 | DONE |
| |
Terms ends for all |
| Dec 18, 2020 |
| except UCD Law 12/12, UCSD 12/19, UCSF 12/31 | |
Winter quarter instruction begins Spring semester instruction begins |
| January 4-19, 2021 |
| winter quarter: UCD, UCI, UCLA, UCR, UCSB, UCSC, UCSD, except UCSF 1/1 spring semester: UCD Law 1/11, UCB and UCM 1/19 | |
Test load start | Ex Libris Migration Team | Jan 3, 2021 | DONE | ||
Ex Libris config overview meeting [III, Voyager and WMS] | Ex Libris | Jan 7, 2021 | DONE |
| |
Configuration meetings | Ex Libris/UC | Jan 8-15, 2021 | DONE |
| |
Draft configuration forms due [III, Voyager and WMS] | UC | Jan 22, 2021 | DONE |
| |
Final configuration forms due [includes EZProxy & Connexion in config case] | UC | Feb 5, 2021 | DONE |
| |
Final Fulfillment Network Group form due | UC | Feb 5, 2021 | DONE |
| |
Test load data and Alma environment delivery - expected | Ex Libris | Feb 19, 2021 | DONE | Delivered early on Feb 11 except for UC Merced which was delivered Feb 24. | |
Primo VE environment delivery | Ex Libris | Feb 26, 2021 | DONE | Delivered early on Feb 25 except for UC Merced which was delivered Feb 27. | |
Primo VE review and refine work | UC | March to May 2021 | DONE | ||
Complete Primo VE review and refine work | UC | March to May 2021 | DONE |
| |
Day 1 Third-Party integrations work | Ex Libris / UC | March to May 2021 | DONE |
| |
Winter quarter ends |
| Mar 19, 2021 |
| except UCSD 3/20, UCSF 3/28 | |
Spring quarter instruction begins |
| Mar 29, 2021 |
| UCD, UCI, UCLA, UCR, UCSB, UCSC, UCSD, UCSF | |
Alma / Primo VE Authentication Configuration Completed | Ex Libris / UC | Apr 30, 2021 | Done | was March 31, 2021 | |
Alma / Primo VE Authorization Configuration Completed | Ex Libris / UC | Apr 30, 2021 | done | was March 31, 2021 | |
Alma SIS Set-up and Testing Complete | Ex Libris / UC | Apr 30, 2021 | Done | Completed June 10 | |
Alma functional workshops | Ex Libris / SILS Internal Training Group | March-May 2021 | done | Analytics workshop will be held post go-live | |
Full cutover plan delivered | Ex Libris | May 6, 2021 | Done |
| |
Complete the Go-Live Readiness Checklist [III, Voyager, WMS, CDL] | UC | May 17, 2021 | done |
| |
Complete Day 1 Third-Party Integrations | Ex Libris / UC | May 31, 2021 | done | ||
Spring term ends for all |
| Jun 11, 2021 |
| except UCD Law 5/15, UCD and UCSC 6/10, UCSF 6/ | |
Cutover cases have been set up with the same primary contact as your Test Load cases. Please inform EXL if there are any any changes needed - via your Cutover case. | UC | Jun 11, 2021 | DONE |
| |
Inform EXL if you plan to perform FY rollover prior to Cutover - via your Cutover case [Alma Campuses] OR If you are migrating ACQ, inform EXL if you plan to perform FY rollover in your ILS prior to Cutover - via your Cutover case [UCB, UCLA, UCSD, UCSF] | UC | Jun 11, 2021 | DONE |
| |
Inform EXL if you plan to opt-out of ProQuest Activations at Cutover via your Cutover case [III, Voyager, WMS] | UC | Jun 11, 2021 | DONE |
| |
Confirm that you can access your MFT shares or report issues via your Cutover Case |
The SILS mission is to transform library services and operations through innovation and collaboration. The future is shared!